The Build May Get Harder. The Need Does Not Go Away.

builder-harder

Voters sent a clear message about data centers on Tuesday. We take it seriously. But data centers are one node in a larger AI-infrastructure build: chips, networks, power, cooling, sites and the capital that funds them. We have to look past the heavy rhetoric to what the policy can actually do. The election changes the delivery path, the cost allocation and the timing of the build. It does not erase the demand.


The short version

  • Divided government points to two years of headlines and hearings, not a new statutory regime.
  • Policy bites hardest on the physical delivery path. The first-order risk is approval and location for 2028 data-center capacity. Most of the 2027 build is too far along to stop.
  • Policy is moving cost and execution risk onto developers. That favors approved power, existing capacity, interconnection and builders that can fund themselves.
  • Demand is still on a steep path. Public estimates put 2028 data-center electricity use at about 1.8 to 3.3 times the 2023 level.
  • Strong AI demand does not guarantee strong supplier returns. Financing, customer concentration, cash conversion and valuation decide who earns them.
  • We are in the early innings of a technology rebuild. The opportunity sits in constrained areas with pricing power, durable cash flows and equity duration.

Two kinds of evidence run through this note, and we label both. External Evidence marks what public sources and market data show. Westwood View marks our interpretation. We keep them apart on purpose. The facts are the same for everyone. What we do with them is our job.

What Changed, and What Did Not

The vote moved the politics more than the physics. Here is how we separate the two.

Where the Election Touches the AI Stack

Westwood View

Divided government rarely produces sweeping law. We expect two years of oversight, hearings, confirmation fights and must-pass bargaining. The more important shift is closer to the ground. States, utilities and localities decide where capacity goes, what it pays for power and who funds the grid upgrade. Texas is the largest swing factor because so much planned capacity sits there. Underwrite the permit and the power contract, not the election map.

layer-of-build